TUBE PLUG,EXCHANGER,MODEL XG57,GRAPHITE

Material 4100093574 · TUBE PLUG · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4100093574
Category
TUBE PLUG
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
RAJAWALI INSTRUMEN INTERNASIONAL PT
Lead time
85 d · P80 151 d
Unit price
Rp 321,954

Recommendation

  • 1.Forecast 2.1 EA/year: 2.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~85 days; expected demand during lead time 0.5.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
  • 4.On hand 2 + on order 1 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 151 days and the fastest seen in its category 29 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 1.9M · order by 01 Oct 2026
Expected arrival ≈ 85 days
Long-leadLast turnaround used 1Single sourceOpen PO
On hand / on order
2 / 1
next delivery 24 Mar 2027
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
9
order qty 3
Service level
99.9%
stockout risk now 1%
Unit price
Rp 321,954
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 252 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 433.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~29 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_HE-693B
ETHYLENE EXCHANGER
A131.08
PX_HE-397A
GASOLINE REBOILER
B120.65

Lead time and procurement

Lead time 85 ± 62 days (PO history + category, 2 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
21 Sept 2026PR05
Project / turnaround
1Rp 325,56424 Mar 2027
open
184 d
08 Jul 2026PR03
Regular replenishment
2Rp 318,34318 Jul 202610 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026MediumPX_HE-693BRetubing HE-693B
19 Oct 2025LowPX_HE-397ALeak from packing
02 Oct 2025MediumPX_HE-693BHE-693B fouling
07 May 2025MediumPX_HE-397ALeak from packing
03 May 2025HighPX_HE-693B[MSI-B-25-ETN-117/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
22 Jan 20263206000038371Other maintenance
24 Dec 20251203000033370Turnaround