TUBE PLUG,EXCHANGER,TYPE NG175,A182F11
Material 4100093970 · TUBE PLUG · Plant 1000
BMonitorTAM reserve
- Material
- 4100093970
- Category
- TUBE PLUG
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- B (1 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 77 d · P80 151 d
- Unit price
- Rp 505,158 (est.)
Recommendation
- 1.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~77 days; expected demand during lead time 0.0.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Used only during the last turnaround (2 EA): keep it for the next one instead of treating it as slow-moving.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Last turnaround used 2Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
2 / 3
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 505,158
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (2 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 23.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~29 days.
Installed on 3 functional locations
1 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-354D INHIBITOR PREHEATER | B | 2 | 3 | 1.08 |
| PX_HE-1192 SLOP OIL EXCHANGER | C | 1 | 7 | 2.36 |
| PX_HE-593C REFLUX REBOILER | C | 1 | 1 | 0.22 |
Lead time and procurement
Lead time 77 ± 62 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Medium | PX_HE-354D | Cleaning HE-354D |
| 10 Sept 2026 | Medium | PX_HE-1192 | HE-1192 fouling |
| 30 Jul 2026 | Medium | PX_HE-1192 | HE-1192 tube leak |
| 17 Feb 2026 | Medium | PX_HE-354D | HE-354D tube leak |
| 07 Feb 2026 | Emergency | PX_HE-1192 | Cleaning HE-1192 |
| 01 Feb 2026 | Medium | PX_HE-1192 | HE-1192 fouling |
| 07 Jan 2026 | Low | PX_HE-1192 | Retubing HE-1192 |
| 04 Jan 2026 | High | PX_HE-1192 | Painting HE-1192 |
| 13 Aug 2025 | Medium | PX_HE-593C | Install scaffolding at HE-593C |
| 24 May 2025 | Medium | PX_HE-354D | Cleaning HE-354D |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Nov 2025 | 1 | 203000035490 | Turnaround |
| 10 Nov 2025 | 1 | 203000035490 | Turnaround |