DEMISTER PAD,MODEL WB275,A105
Material 4100096569 · DEMISTER PAD · Plant 1000
ALong-leadReorderNormalSlow-moving
- Material
- 4100096569
- Category
- DEMISTER PAD
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 7 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 127 d · P80 215 d
- Unit price
- Rp 5.3M
Recommendation
- 1.Forecast 2.2 EA/year: 2.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~127 days; expected demand during lead time 0.7.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
- 4.On hand 3 + on order 0 is at or below the reorder point: order 6 now.
- 5.Long lead time: 80% of deliveries took up to 215 days and the fastest seen in its category 34 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 7 FuncLoc(s), 5 of them criticality A/B.
- 7.ML early warning: 50% probability of demand in the next 90 days.
Proposed purchase requisition
6 EA
Rp 31.8M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Long-leadML early warningSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
9
order qty 3
Service level
99.9%
stockout risk now 5%
Unit price
Rp 5.3M
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 300 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 781.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~34 days.
Installed on 7 functional locations
5 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_CL-658 RICH AMINE STRIPPER | A | 3 | 1 | 0.38 |
| PX_VD-973 QUENCH OIL ACCUMULATOR | A | 1 | 1 | 0.08 |
| PX_VD-1350 FUEL OIL SURGE DRUM | A | 1 | 0 | 0.08 |
| PX_CL-348 SEAL OIL TOWER | B | 1 | 3 | 0.81 |
| PX_VD-1756A C3 RECYCLE SEPARATOR | B | 2 | 0 | 0.08 |
| PX_CL-1165 HYDROGEN TOWER | S | 1 | 5 | 1.23 |
| PX_VD-1305A FUEL OIL DRUM | S | 1 | 2 | 0.51 |
Lead time and procurement
Lead time 127 ± 81 days (PO history, 3 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 30 Jul 2026 | PR06 Regular replenishment | 1 | Rp 5.6M | 30 Sept 2026 | 62 d |
| 01 May 2026 | PR03 Regular replenishment | 1 | Rp 5.3M | 17 Sept 2026 | 139 d |
| 11 Jun 2025 | PR03 Regular replenishment | 1 | Rp 5.2M | 03 Mar 2026 | 265 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 10 Sept 2026 | Low | PX_CL-348 | Leak from packing |
| 15 Mar 2026 | Low | PX_CL-348 | Install scaffolding at CL-348 |
| 31 Jan 2026 | Medium | PX_VD-1305A | VD-1305A level glass broken |
| 13 Jan 2026 | High | PX_CL-1165 | Install scaffolding at CL-1165 |
| 07 Dec 2025 | Medium | PX_CL-1165 | Replace lamp as per PM finding |
| 01 Dec 2025 | Medium | PX_CL-1165 | Install scaffolding at CL-1165 |
| 27 Sept 2025 | Medium | PX_CL-1165 | CL-1165 DP high |
| 12 Aug 2025 | Medium | PX_CL-658 | Install scaffolding at CL-658 |
| 03 Aug 2025 | Low | PX_CL-1165 | Install scaffolding at CL-1165 |
| 22 May 2025 | Medium | PX_CL-348 | PSM25/[MSI-B-25-GCX-389] Permanent repai |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 05 Dec 2025 | 2 | 201000031139 | Corrective |