DEMISTER PAD,MODEL WB275,A105

Material 4100096569 · DEMISTER PAD · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4100096569
Category
DEMISTER PAD
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 7 FuncLocs A/B)
Supplier
CAHAYA LOGAM PRATAMA PT
Lead time
127 d · P80 215 d
Unit price
Rp 5.3M

Recommendation

  • 1.Forecast 2.2 EA/year: 2.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~127 days; expected demand during lead time 0.7.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
  • 4.On hand 3 + on order 0 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 215 days and the fastest seen in its category 34 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 7 FuncLoc(s), 5 of them criticality A/B.
  • 7.ML early warning: 50% probability of demand in the next 90 days.
Proposed purchase requisition
6 EA
Rp 31.8M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Long-leadML early warningSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
9
order qty 3
Service level
99.9%
stockout risk now 5%
Unit price
Rp 5.3M
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 300 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 781.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~34 days.

Installed on 7 functional locations

5 with criticality A/B · 10 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_CL-658
RICH AMINE STRIPPER
A310.38
PX_VD-973
QUENCH OIL ACCUMULATOR
A110.08
PX_VD-1350
FUEL OIL SURGE DRUM
A100.08
PX_CL-348
SEAL OIL TOWER
B130.81
PX_VD-1756A
C3 RECYCLE SEPARATOR
B200.08
PX_CL-1165
HYDROGEN TOWER
S151.23
PX_VD-1305A
FUEL OIL DRUM
S120.51

Lead time and procurement

Lead time 127 ± 81 days (PO history, 3 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
30 Jul 2026PR06
Regular replenishment
1Rp 5.6M30 Sept 202662 d
01 May 2026PR03
Regular replenishment
1Rp 5.3M17 Sept 2026139 d
11 Jun 2025PR03
Regular replenishment
1Rp 5.2M03 Mar 2026265 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
10 Sept 2026LowPX_CL-348Leak from packing
15 Mar 2026LowPX_CL-348Install scaffolding at CL-348
31 Jan 2026MediumPX_VD-1305AVD-1305A level glass broken
13 Jan 2026HighPX_CL-1165Install scaffolding at CL-1165
07 Dec 2025MediumPX_CL-1165Replace lamp as per PM finding
01 Dec 2025MediumPX_CL-1165Install scaffolding at CL-1165
27 Sept 2025MediumPX_CL-1165CL-1165 DP high
12 Aug 2025MediumPX_CL-658Install scaffolding at CL-658
03 Aug 2025LowPX_CL-1165Install scaffolding at CL-1165
22 May 2025MediumPX_CL-348PSM25/[MSI-B-25-GCX-389] Permanent repai

Recent goods issues

Posting dateQtyOrderOrder type
05 Dec 20252201000031139Corrective