Sparely
DU

DEMISTER PAD,MODEL MN640,VITON

Material 4100097215 · DEMISTER PAD · Plant 1000

ALong-leadReduceSlow-moving
Material
4100097215
Category
DEMISTER PAD
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
CAHAYA INDUSTRI JAYA PT
Lead time
116 d · P80 179 d
Unit price
Rp 7.2M

Recommendation

  • 1.Forecast 1.2 EA/year: 1.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~116 days; expected demand during lead time 0.4.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.Stock 9 exceeds the level to keep (6) by 3.
  • 5.Long lead time: 80% of deliveries took up to 179 days and the fastest seen in its category 34 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Long-leadLast turnaround used 2Single sourceOpen PO
On hand / on order
9 / 1
next delivery 30 Apr 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 7.2M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 257 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (2 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 419.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~34 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_CL-961
LEAN AMINE COLUMN
A131.23
PX_VD-855B
QUENCH OIL SEPARATOR
A100.08

Lead time and procurement

Lead time 116 ± 76 days (PO history, 3 PO lines) · on-time 45%

PR dateTypeQtyUnit priceDeliveryLead time
03 Sept 2026PR06
Regular replenishment
1Rp 7.2M30 Apr 2027
open
239 d
11 Jul 2026PR03
Regular replenishment
1Rp 7.2M19 Sept 202670 d
31 May 2026PR06
Regular replenishment
2Rp 7.4M29 Aug 202690 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026MediumPX_CL-961[MSI-B-26-UAX-291] Permanent repair
30 Aug 2026LowPX_CL-961CL-961 DP high
19 May 2025MediumPX_CL-961CL-961 DP high

Recent goods issues

Posting dateQtyOrderOrder type
17 Jan 20262201000037028Corrective
16 Dec 20252203000039452Turnaround