SCREW,TAPPING,M3X16MM,SS304
Material 4100098169 · SCREW · Plant 1000
AReduceExcess
- Material
- 4100098169
- Category
- SCREW
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 11 FuncLocs A/B)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 25 d · P80 32 d
- Unit price
- Rp 311
Recommendation
- 1.Forecast 3,233 EA/year: 3,233 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~25 days; expected demand during lead time 225.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 819, order up to 4,053.
- 4.Stock 4,748 exceeds the level to keep (4,053) by 695.
- 5.Installed on 11 FuncLoc(s), 6 of them criticality A/B.
- 6.ML early warning: 99% probability of demand in the next 90 days.
ML early warningLast turnaround used 870Single sourceAbnormal consumptionSame description as 2 other material numbers
On hand / on order
4,748 / 0
no open PO
Today Min / Max
1,610 / 3,344
static parameters in BoM
Rec. Min (reorder point)
819
safety stock 595
Rec. Max
4,053
order qty 3,234
Service level
99.9%
stockout risk now 0%
Unit price
Rp 311
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 18 days ago, 73 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1,010 units) excluded from the baseline.
Demand pattern Erratic · 44 issue days · 5 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 11 functional locations
6 with criticality A/B · 21,661 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1,500 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1,500 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 50 | 71 | 28.72 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 5,037 | 29 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 50 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1,500 | 23 | 9.01 |
| PX_JBX-279 JUNCTION BOX | C | 50 | 1 | 0.01 |
| PX_JBX-1190A JUNCTION BOX | C | 5,037 | 0 | 0.01 |
| PX_JBX-1364 JUNCTION BOX (EXP) | C | 400 | 0 | 0.01 |
| PX_JBX-938A JUNCTION BOX | C | 1,500 | 0 | 0.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 5,037 | 41 | 14.58 |
Lead time and procurement
Lead time 25 ± 9 days (PO history, 14 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 21 Aug 2026 | PR03 Regular replenishment | 6,979 | Rp 306 | 13 Sept 2026 | 23 d |
| 18 Aug 2026 | PR06 Regular replenishment | 4,302 | Rp 313 | 28 Aug 2026 | 10 d |
| 28 Jun 2026 | PR03 Regular replenishment | 4,614 | Rp 306 | 31 Jul 2026 | 33 d |
| 30 Dec 2025 | PR06 Regular replenishment | 3,176 | Rp 309 | 22 Jan 2026 | 23 d |
| 08 Dec 2025 | PR03 Regular replenishment | 2,620 | Rp 319 | 28 Dec 2025 | 20 d |
| 11 Nov 2025 | PR03 Regular replenishment | 7,649 | Rp 302 | 12 Dec 2025 | 31 d |
| 17 Sept 2025 | PR04 Regular (other) | 8,553 | Rp 308 | 26 Oct 2025 | 39 d |
| 10 Sept 2025 | PR03 Regular replenishment | 7,143 | Rp 318 | 08 Oct 2025 | 28 d |
| 22 Aug 2025 | PR06 Regular replenishment | 2,803 | Rp 313 | 23 Sept 2025 | 32 d |
| 05 Aug 2025 | PR03 Regular replenishment | 5,359 | Rp 309 | 17 Sept 2025 | 43 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 13 Sept 2026 | 50 | 204000000772 | Preventive |
| 23 Aug 2026 | 20 | 201000010546 | Corrective |
| 21 Aug 2026 | 200 | 201000000652 | Corrective |
| 11 Aug 2026 | 5,000 | 204000010836 | Preventive |
| 10 Jul 2026 | 50 | 201000002156 | Corrective |
| 01 Jul 2026 | 1,000 | 201000017983 | Corrective |
| 22 Jun 2026 | 200 | 209000014083 | Other maintenance |
| 18 Apr 2026 | 100 | 201000006270 | Corrective |
| 14 Mar 2026 | 50 | 204000017829 | Preventive |
| 09 Mar 2026 | 100 | 201000024115 | Corrective |
| 15 Feb 2026 | 20 | 201000004102 | Corrective |
| 15 Feb 2026 | 100 | 201000034114 | Corrective |
| 29 Jan 2026 | 50 | 201000038273 | Corrective |
| 19 Jan 2026 | 50 | 201000022831 | Corrective |
| 13 Jan 2026 | 50 | 201000005022 | Corrective |