SCREW,TAPPING,M6X20MM,SS304
Material 4100099527 · SCREW · Plant 1000
SMonitorInsurance gap
- Material
- 4100099527
- Category
- SCREW
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- S (0 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 20 d · P80 33 d
- Unit price
- Rp 1,538 (est.)
Recommendation
- 1.Forecast 70 EA/year: 70 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~20 days; expected demand during lead time 3.8.
- 3.A 96.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 117.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
117
order qty 117
Service level
96.8%
stockout risk now 3%
Unit price
Rp 1,538
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~10 days.
Installed on 1 functional locations
0 with criticality A/B · 50 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-110 CRACKING FURNACE BF-110 | S | 50 | 41 | 14.58 |
Lead time and procurement
Lead time 20 ± 12 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
| 03 Sept 2026 | Low | PX_BF-110 | Hot spot at convection BF-110 |
| 03 Sept 2026 | Medium | PX_BF-110 | Thermograph wall BF-110 |
| 01 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 30 Aug 2026 | Low | PX_BF-110 | Leak from packing |
| 07 Aug 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 07 Aug 2026 | Medium | PX_BF-110 | Painting BF-110 |
Recent goods issues
Never issued in the 17-month history.