BOLT,ANCHOR,SIZE PF180,A105
Material 4100099761 · BOLT · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100099761
- Category
- BOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 7 FuncLocs A/B)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 29 d · P80 53 d
- Unit price
- Rp 10,135
Recommendation
- 1.Forecast 22 EA/year: 22 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~29 days; expected demand during lead time 1.8.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 30.
- 4.On hand 3 + on order 0 is at or below the reorder point: order 27 now.
- 5.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
27 EA
Rp 273,645 · order by 01 Oct 2026
Expected arrival ≈ 29 days
Single source
On hand / on order
3 / 0
no open PO
Today Min / Max
2 / 5
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
30
order qty 23
Service level
99.9%
stockout risk now 10%
Unit price
Rp 10,135
PO history
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 62 days ago, 52 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 7 functional locations
4 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1 | 114 | 42.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 3 | 73 | 27.01 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1 | 23 | 9.01 |
| PX_PP-1049-CST CONCRETE STRUCTURE PP-1049 | C | 1 | 0 | 0.19 |
| PX_PP-1101A-CST CONCRETE STRUCTURE PP-1101A | C | 1 | 0 | 0.19 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 1 | 23 | 9.44 |
Lead time and procurement
Lead time 29 ± 19 days (PO history + category, 1 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Mar 2026 | PR06 Regular replenishment | 2 | Rp 10,135 | 07 May 2026 | 46 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 31 Jul 2026 | 1 | 201000005649 | Corrective |
| 23 Dec 2025 | 1 | 201000011788 | Corrective |