BOLT,ANCHOR,MODEL SF916,GRAPHITE
Material 4100099802 · BOLT · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100099802
- Category
- BOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 53 d
- Unit price
- Rp 20,009 (est.)
Recommendation
- 1.Forecast 2.0 EA/year: 2.0 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~23 days; expected demand during lead time 0.1.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.No issue in 17 months, but it protects critical equipment: keep it.
- 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
100.0%
stockout risk now 0%
Unit price
Rp 20,009
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 31 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 391.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 4 functional locations
2 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_PP-1101A-CST CONCRETE STRUCTURE PP-1101A | C | 1 | 0 | 0.19 |
| PX_PP-416A-CST CONCRETE STRUCTURE PP-416A | C | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 23 ± 19 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 19 Sept 2026 | Medium | PX_BF-106 | Cleaning burner BF-106 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 15 Sept 2026 | Medium | PX_BF-106 | Install cover plate BF-106 |
| 14 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 10 Sept 2026 | Medium | PX_BF-106 | Replace burner tip BF-106 |
Recent goods issues
Never issued in the 17-month history.