BOLT,ANCHOR,TYPE NF264,MONEL
Material 4100100048 · BOLT · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100100048
- Category
- BOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 23 d · P80 53 d
- Unit price
- Rp 20,009 (est.)
Recommendation
- 1.Forecast 8.2 EA/year: 8.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~23 days; expected demand during lead time 0.5.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 13.
- 4.On hand 4 + on order 0 is at or below the reorder point: order 9 now.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
9 EA
Rp 180,081 · order by 01 Oct 2026
Expected arrival ≈ 23 days
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
13
order qty 9
Service level
100.0%
stockout risk now 0%
Unit price
Rp 20,009
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 21 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
Lead time and procurement
Lead time 23 ± 19 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 04 Sept 2026 | High | PX_BF-112 | Install scaffolding at BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 31 Aug 2026 | Medium | PX_BF-112 | Install cover plate for MCP cracking |
| 17 Aug 2026 | Medium | PX_BF-112 | Painting BF-112 |
| 15 Aug 2026 | Low | PX_BF-112 | Decoking follow up BF-112 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 10 Sept 2026 | 1 | 201000017022 | Corrective |