BOLT,ANCHOR,TYPE NU403,INCOLOY
Material 4100100149 · BOLT · Plant 1000
AReduceExcess
- Material
- 4100100149
- Category
- BOLT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- SURYA PERKASA GLOBAL PT
- Lead time
- 20 d · P80 53 d
- Unit price
- Rp 25,808
Recommendation
- 1.Forecast 7.7 EA/year: 7.7 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~20 days; expected demand during lead time 0.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 12.
- 4.Stock 39 exceeds the level to keep (12) by 27.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Single source
On hand / on order
39 / 0
no open PO
Today Min / Max
2 / 5
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
12
order qty 8
Service level
100.0%
stockout risk now 0%
Unit price
Rp 25,808
PO history
ML early warning: 21% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 158 days ago, 20 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_PP-1101A-CST CONCRETE STRUCTURE PP-1101A | C | 1 | 0 | 0.19 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1 | 41 | 14.58 |
Lead time and procurement
Lead time 20 ± 19 days (PO history + category, 1 PO lines) · on-time 49%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Jul 2025 | PR03 Regular replenishment | 2 | Rp 25,808 | 20 Jul 2025 | 11 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
| 04 Sept 2026 | Medium | PX_BF-104 | Replace burner tip BF-104 |
| 03 Sept 2026 | Low | PX_BF-110 | Hot spot at convection BF-110 |
| 03 Sept 2026 | Medium | PX_BF-110 | Thermograph wall BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Apr 2026 | 2 | 201000031464 | Corrective |
| 27 Feb 2026 | 1 | 201000033452 | Corrective |
| 13 Dec 2025 | 1 | 201000021360 | Corrective |