Sparely
DU

SCREEN,WIRE,MODEL DN944,A182F11

Material 4100105207 · SCREEN · Plant 1000

AReduceSlow-moving
Material
4100105207
Category
SCREEN
Base unit
SHT
MRP type
Stock Item
Criticality
A (3 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
48 d · P80 65 d
Unit price
Rp 421,534 (est.)

Recommendation

  • 1.Forecast 0.7 SHT/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~48 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 6 exceeds the level to keep (3) by 3.
  • 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
6 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 421,534
Category + unit estimate
ML early warning: 13% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 373 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 289.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~21 days.

Installed on 5 functional locations

3 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_VD-694A
C3 RECYCLE ACCUMULATOR
A130.93
PX_VD-1729
PROPYLENE KO DRUM
A120.08
PX_VD-1210
C4 PRODUCT ACCUMULATOR
A100.08
PX_CL-1546
LUBE OIL COLUMN
S100.38
PX_CL-899
SLOP OIL COLUMN
S100.38

Lead time and procurement

Lead time 48 ± 28 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Jun 2026LowPX_VD-694ALeak from packing
07 Mar 2026MediumPX_VD-1729Install scaffolding at VD-1729
01 Oct 2025MediumPX_VD-694AInspect VD-694A
09 May 2025MediumPX_VD-694APSM25/Replace lamp as per PM finding
06 May 2025MediumPX_VD-1729Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
23 Sept 20251201000009247Corrective