SCREEN,WIRE,TYPE MU811,VITON
Material 4100105273 · SCREEN · Plant 1000
AReorderCriticalStockout
- Material
- 4100105273
- Category
- SCREEN
- Base unit
- SHT
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- NUSA ELEKTRIK SENTOSA PT
- Lead time
- 52 d · P80 65 d
- Unit price
- Rp 319,462
Recommendation
- 1.Forecast 3.0 SHT/year: 3.0 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~52 days; expected demand during lead time 0.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 8.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 8 now.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
8 SHT
Rp 2.6M · order by 01 Oct 2026
Expected arrival ≈ 52 days
Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
8
order qty 3
Service level
100.0%
stockout risk now 24%
Unit price
Rp 319,462
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 41 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 869.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~21 days.
Installed on 3 functional locations
2 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_VD-1729 METHANE KO DRUM | A | 1 | 0 | 0.08 |
| PY_CL-890 CONDENSATE SCRUBBER | B | 1 | 3 | 1.23 |
| PX_CL-443 COOLING WATER SCRUBBER | S | 1 | 6 | 2.52 |
Lead time and procurement
Lead time 52 ± 28 days (PO history + category, 2 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Dec 2025 | PR05 Project / turnaround | 2 | Rp 316,889 | 16 Feb 2026 | 66 d |
| 07 Jun 2025 | PR04 Regular (other) | 1 | Rp 322,035 | 25 Jul 2025 | 48 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 03 Sept 2026 | Medium | PX_CL-443 | Replace lamp as per PM finding |
| 09 Jul 2026 | High | PX_CL-443 | CL-443 DP high |
| 25 Jun 2026 | Medium | PX_CL-443 | Leak from packing |
| 20 Jun 2026 | Low | PY_CL-890 | Leak from packing |
| 01 May 2026 | Medium | PX_CL-443 | Install scaffolding at CL-443 |
| 31 Jan 2026 | Medium | PY_CL-890 | Leak from packing |
| 30 Jan 2026 | Low | PX_CL-443 | Replace lamp as per PM finding |
| 18 Jun 2025 | Medium | PX_CL-443 | PSM25/CL-443 DP high |
| 31 May 2025 | Low | PY_CL-890 | Inspect CL-890 internal |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Aug 2026 | 2 | 201000019311 | Corrective |
| 02 May 2026 | 1 | 201000030476 | Corrective |