OIL,LUBRICANT,ISO VG 46,SYNTHETIC,209L
Material 4100107096 · OIL · Plant 1000
AReorderCriticalBelow reorder point
- Material
- 4100107096
- Category
- OIL
- Base unit
- L
- MRP type
- Stock Item
- Criticality
- A (7 of 10 FuncLocs A/B)
- Supplier
- ANUGRAH INSTRUMEN SENTOSA PT
- Lead time
- 35 d · P80 50 d
- Unit price
- Rp 214,489
Recommendation
- 1.Forecast 97 L/year: 97 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~35 days; expected demand during lead time 9.3.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 48, order up to 131.
- 4.On hand 5 + on order 0 is at or below the reorder point: order 126 now.
- 5.Installed on 10 FuncLoc(s), 7 of them criticality A/B.
- 6.ML early warning: 90% probability of demand in the next 90 days.
Proposed purchase requisition
126 L
Rp 27.0M · order by 01 Oct 2026
Expected arrival ≈ 35 days
ML early warningLast turnaround used 229Single sourceAbnormal consumption
On hand / on order
5 / 0
no open PO
Today Min / Max
25 / 64
static parameters in BoM
Rec. Min (reorder point)
48
safety stock 39
Rec. Max
131
order qty 83
Service level
100.0%
stockout risk now 69%
Unit price
Rp 214,489
PO history
ML early warning: 90% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 7 days ago, 14 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (249 units) excluded from the baseline.
Demand pattern Erratic · 16 issue days · 5 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 10 functional locations
7 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-717 FLUSHING OIL COMPRESSOR | A | 1 | 9 | 4.00 |
| PX_KC-396 WASH WATER BLOWER | A | 1 | 3 | 1.43 |
| PX_PP-1574B QUENCH WATER PUMP | A | 1 | 2 | 0.62 |
| PX_KC-155D CAUSTIC BLOWER | A | 1 | 0 | 0.57 |
| PX_PP-1099 LUBE OIL PUMP | A | 1 | 0 | 0.19 |
| PX_KC-284A WASH WATER COMPRESSOR | B | 1 | 2 | 1.43 |
| PX_PP-1370C FUEL OIL PUMP | B | 1 | 0 | 0.19 |
| PX_KC-843 FUEL OIL COMPRESSOR | S | 1 | 21 | 8.28 |
| PX_KC-264A C4 PRODUCT FAN | S | 1 | 5 | 1.85 |
| PX_KC-511C FUEL OIL FAN | S | 1 | 1 | 0.57 |
Lead time and procurement
Lead time 35 ± 22 days (PO history, 8 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 28 Jul 2026 | PR03 Regular replenishment | 291 | Rp 211,000 | 09 Sept 2026 | 43 d |
| 10 Jun 2026 | PR03 Regular replenishment | 171 | Rp 220,159 | 04 Jul 2026 | 24 d |
| 28 May 2026 | PR06 Regular replenishment | 212 | Rp 219,585 | 14 Jun 2026 | 17 d |
| 22 May 2026 | PR06 Regular replenishment | 184 | Rp 206,323 | 19 Jun 2026 | 28 d |
| 05 May 2026 | PR01 Import / long-lead | 327 | Rp 217,977 | 07 Jun 2026 | 33 d |
| 06 Dec 2025 | PR03 Regular replenishment | 191 | Rp 209,292 | 28 Dec 2025 | 22 d |
| 17 Nov 2025 | PR03 Regular replenishment | 312 | Rp 220,660 | 19 Feb 2026 | 94 d |
| 05 May 2025 | PR03 Regular replenishment | 205 | Rp 206,972 | 28 Jun 2025 | 54 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Medium | PX_KC-396 | Replace lamp as per PM finding |
| 21 Sept 2026 | Low | PX_KC-717 | Leak from packing |
| 21 Sept 2026 | Medium | PX_KC-843 | Painting KC-843 |
| 16 Sept 2026 | Low | PX_KC-843 | Inspect coupling KC-843 |
| 29 Aug 2026 | Medium | PX_KC-843 | Replace lamp as per PM finding |
| 26 Aug 2026 | Medium | PX_KC-843 | [MSI-B-26-RLH-211] Permanent repair |
| 14 Aug 2026 | Medium | PX_KC-843 | KC-843 lube oil filter DP high |
| 10 Aug 2026 | Medium | PX_PP-1574B | Overhaul PP-1574B |
| 08 Aug 2026 | Medium | PX_KC-717 | Repair insulation KC-717 |
| 06 Aug 2026 | Medium | PX_KC-843 | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Sept 2026 | 20 | 209000029477 | Other maintenance |
| 23 Sept 2026 | 4 | 209000029477 | Other maintenance |
| 24 Aug 2026 | 5 | 201000000994 | Corrective |
| 12 Jul 2026 | 1 | 201000033008 | Corrective |
| 26 Jun 2026 | 1 | 201000001753 | Corrective |
| 25 Jun 2026 | 1 | 201000016931 | Corrective |
| 01 Apr 2026 | 4 | 201000031203 | Corrective |
| 04 Mar 2026 | 20 | 201000026477 | Corrective |
| 08 Feb 2026 | 20 | 203000018609 | Turnaround |
| 05 Feb 2026 | 4 | 201000017210 | Corrective |
| 28 Jan 2026 | 4 | 203000033471 | Turnaround |
| 27 Dec 2025 | 1 | 201000031912 | Corrective |
| 29 Nov 2025 | 200 | 203000032713 | Turnaround |
| 22 Nov 2025 | 5 | 203000037311 | Turnaround |
| 17 Nov 2025 | 1 | 204000038991 | Preventive |