OIL,LUBRICANT,ISO VG 46,MINERAL,20L
Material 4100107205 · OIL · Plant 1000
CReduceExcess
- Material
- 4100107205
- Category
- OIL
- Base unit
- L
- MRP type
- Stock Item
- Criticality
- C (0 of 4 FuncLocs A/B)
- Supplier
- DUTA ENERGI ABADI PT
- Lead time
- 44 d · P80 46 d
- Unit price
- Rp 226,686
Recommendation
- 1.Forecast 386 L/year: 386 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~44 days; expected demand during lead time 46.
- 3.A 76.3% service level gives the lowest holding + downtime-risk cost: reorder at 50, order up to 210.
- 4.Stock 417 exceeds the level to keep (210) by 207.
- 5.ML early warning: 89% probability of demand in the next 90 days.
ML early warningSingle sourceAbnormal consumption
On hand / on order
417 / 0
no open PO
Today Min / Max
194 / 469
static parameters in BoM
Rec. Min (reorder point)
50
safety stock 4
Rec. Max
210
order qty 160
Service level
76.3%
stockout risk now 0%
Unit price
Rp 226,686
PO history
ML early warning: 89% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 12 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (20 units) excluded from the baseline.
Demand pattern Lumpy · 13 issue days · 5 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 51.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~13 days.
Installed on 4 functional locations
0 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1782A BFW PUMP | C | 1 | 2 | 0.62 |
| PY_PP-1800A DEMIN WATER PUMP | C | 1 | 0 | 0.19 |
| PX_KC-236B DILUTION STEAM FAN | S | 1 | 1 | 0.57 |
| PX_KC-293B C4 PRODUCT COMPRESSOR | S | 1 | 0 | 0.57 |
Lead time and procurement
Lead time 44 ± 31 days (PO history, 6 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 30 Jul 2026 | PR03 Regular replenishment | 463 | Rp 231,137 | 07 Sept 2026 | 39 d |
| 30 Sept 2025 | PR03 Regular replenishment | 154 | Rp 227,957 | 09 Feb 2026 | 132 d |
| 24 Jun 2025 | PR03 Regular replenishment | 325 | Rp 230,042 | 09 Aug 2025 | 46 d |
| 22 Jun 2025 | PR03 Regular replenishment | 226 | Rp 225,414 | 31 Jul 2025 | 39 d |
| 17 Jun 2025 | PR03 Regular replenishment | 507 | Rp 213,479 | 28 Jul 2025 | 41 d |
| 30 May 2025 | PR06 Regular replenishment | 281 | Rp 215,367 | 22 Jun 2025 | 23 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 Sept 2025 | Medium | PX_PP-1782A | Leak from packing |
| 07 May 2025 | Low | PX_PP-1782A | Leak from packing |
| 06 May 2025 | Medium | PX_KC-236B | PSM25/Install scaffolding at KC-236B |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 19 Sept 2026 | 4 | 201000033682 | Corrective |
| 27 Jul 2026 | 1 | 201000005182 | Corrective |
| 11 May 2026 | 200 | 201000031468 | Corrective |
| 13 Apr 2026 | 1 | 201000013543 | Corrective |
| 07 Feb 2026 | 20 | 201000015186 | Corrective |
| 22 Jan 2026 | 20 | 201000028010 | Corrective |
| 26 Dec 2025 | 4 | 201000002958 | Corrective |
| 20 Dec 2025 | 200 | 201000016591 | Corrective |
| 12 Dec 2025 | 200 | 201000008455 | Corrective |
| 17 Nov 2025 | 200 | 201000039953 | Corrective |
| 23 Aug 2025 | 20 | 203000020904 | Turnaround |
| 07 Jul 2025 | 5 | 209000008579 | Other maintenance |
| 30 Jun 2025 | 1 | 209000008119 | Other maintenance |
| 02 Jun 2025 | 200 | 201000035755 | Corrective |