OIL,LUBRICANT,ISO VG 68,MINERAL,209L
Material 4100107463 · OIL · Plant 1000
ATransferNormalSlow-moving
- Material
- 4100107463
- Category
- OIL
- Base unit
- L
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 24 d · P80 36 d
- Unit price
- Rp 157,448 (est.)
Recommendation
- 1.Forecast 7.1 L/year: 5.6 unplanned (credibility blend: own history + installed-base prior) + 1.4 from the maintenance plan.
- 2.Lead time ~24 days; expected demand during lead time 1.1 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 12.
- 4.On hand 2 + on order 0 is at or below the reorder point: 10 needed.
- 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
- 6.Identical part 4100108204 holds spare stock: transfer 10 L instead of buying — no purchase needed.
Planned demand in lead timePrice estimatedLead time estimatedSame description as 1 other material number
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
12
order qty 8
Service level
99.9%
stockout risk now 5%
Unit price
Rp 157,448
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 367 days ago, 15 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 5 functional locations
3 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-536A LUBE OIL BLOWER | A | 1 | 11 | 4.42 |
| PX_PP-367C METHANE PUMP | B | 1 | 4 | 1.90 |
| PX_PP-1157 ETHYLENE PUMP | B | 1 | 1 | 0.19 |
| PX_KC-773A REFLUX COMPRESSOR | S | 1 | 25 | 9.99 |
| PX_KC-879A CONDENSATE FAN | S | 1 | 6 | 2.71 |
Lead time and procurement
Lead time 24 ± 13 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Oct 2026 | PX_PP-367C | Lube oil change | 0.72 |
| 02 Apr 2027 | PX_PP-367C | Lube oil change | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 24 Sept 2026 | Low | PX_KC-879A | Inspect coupling KC-879A |
| 22 Sept 2026 | High | PX_KC-536A | Overhaul |
| 15 Sept 2026 | Low | PX_KC-773A | Install scaffolding at KC-773A |
| 07 Sept 2026 | Medium | PX_KC-879A | Replace lamp as per PM finding |
| 23 Aug 2026 | Low | PX_KC-773A | KC-773A bearing temp high |
| 10 Aug 2026 | Low | PX_KC-773A | KC-773A high vibration |
| 09 Aug 2026 | Medium | PX_KC-773A | Inspect coupling KC-773A |
| 08 Aug 2026 | High | PX_KC-536A | KC-536A bearing temp high |
| 03 Aug 2026 | Medium | PX_KC-773A | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 29 Sept 2025 | 1 | 201000005438 | Corrective |