TERMINAL,LUG,PIN,8X6MM,CRIMP
Material 4200000138 · TERMINAL · Plant 1000
AMonitorHealthy
- Material
- 4200000138
- Category
- TERMINAL
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (29 of 56 FuncLocs A/B)
- Supplier
- TIRTA SUPLINDO NUSANTARA PT
- Lead time
- 38 d · P80 49 d
- Unit price
- Rp 1,976
Recommendation
- 1.Forecast 24,439 EA/year: 24,439 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~38 days; expected demand during lead time 2,531.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7,984, order up to 21,605.
- 4.Installed on 56 FuncLoc(s), 29 of them criticality A/B.
- 5.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 3,520Single sourceAbnormal consumptionOpen PO
On hand / on order
2,569 / 52,721
next delivery 02 Oct 2026
Today Min / Max
2,000 / 3,344
static parameters in BoM
Rec. Min (reorder point)
7,984
safety stock 5,454
Rec. Max
21,605
order qty 13,621
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1,976
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 38 issue days in the last 180 days, last issue 1 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 17 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (10,560 units) excluded from the baseline.
Demand pattern Erratic · 153 issue days · 26 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 19.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~9 days.
Installed on 56 functional locations
29 with criticality A/B · 66 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1470A-M MOTOR FOR PP-1470A | A | 1 | 3 | 0.62 |
| PX_PP-438B-CSS CONTROL SWITCH STATION FOR PP-438B-M | A | 1 | 3 | 1.05 |
| PX_PP-606D-M MOTOR FOR PP-606D | A | 1 | 3 | 1.05 |
| PX_PP-1157-M MOTOR FOR PP-1157 | A | 1 | 2 | 0.19 |
| PX_PP-1864A-M MOTOR FOR PP-1864A | A | 1 | 1 | 0.19 |
| PX_PP-1872A-M MOTOR FOR PP-1872A | A | 1 | 1 | 0.19 |
| PX_JBX-1109 JUNCTION BOX | A | 1 | 0 | 0.01 |
| PX_JBX-1296 JUNCTION BOX | A | 1 | 0 | 0.01 |
| PX_PP-1063-M MOTOR FOR PP-1063 | A | 1 | 0 | 0.19 |
| PX_PP-1366A-CSS CONTROL SWITCH STATION FOR PP-1366A-M | A | 1 | 0 | 0.19 |
| PX_PP-1890-M MOTOR FOR PP-1890 | A | 1 | 0 | 0.19 |
| PX_PP-1909A-M MOTOR FOR PP-1909A | A | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 38 ± 21 days (PO history, 50 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 21 Sept 2026 | PR03 Regular replenishment | 25,841 | Rp 1,914 | 22 Oct 2026 open | 31 d |
| 15 Sept 2026 | PR03 Regular replenishment | 26,880 | Rp 2,056 | 02 Oct 2026 open | 17 d |
| 14 Aug 2026 | PR03 Regular replenishment | 13,973 | Rp 1,998 | 17 Sept 2026 | 34 d |
| 04 Aug 2026 | PR03 Regular replenishment | 12,503 | Rp 1,980 | 01 Sept 2026 | 28 d |
| 12 Jul 2026 | PR04 Regular (other) | 26,120 | Rp 2,013 | 18 Aug 2026 | 37 d |
| 01 Jul 2026 | PR03 Regular replenishment | 25,841 | Rp 2,027 | 07 Sept 2026 | 68 d |
| 25 Jun 2026 | PR05 Project / turnaround | 19,840 | Rp 1,889 | 28 Aug 2026 | 64 d |
| 31 May 2026 | PR03 Regular replenishment | 40,269 | Rp 2,000 | 03 Jul 2026 | 33 d |
| 20 May 2026 | PR03 Regular replenishment | 20,494 | Rp 2,008 | 01 Jul 2026 | 42 d |
| 17 May 2026 | PR03 Regular replenishment | 22,845 | Rp 1,921 | 21 Jul 2026 | 65 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Medium | PX_KC-773A-M | Replace lamp as per PM finding |
| 14 Sept 2026 | Medium | PX_PP-438B-CSS | Leak from packing |
| 06 Aug 2026 | Low | PX_PP-744B-M | Painting PP-744B-M |
| 27 Jul 2026 | Medium | PX_PP-1157-M | Install scaffolding at PP-1157-M |
| 16 Jul 2026 | Medium | PX_PP-606D-M | Leak from packing |
| 16 Mar 2026 | Medium | PX_PP-606D-M | PP-606D-M high temp |
| 20 Jan 2026 | Medium | PX_PP-479-M | Painting PP-479-M |
| 23 Dec 2025 | High | PX_KC-773A-M | Replace lamp as per PM finding |
| 07 Dec 2025 | Medium | PX_PP-1470A-M | PP-1470A-M high temp |
| 29 Nov 2025 | Medium | PX_PP-1470A-M | Install scaffolding at PP-1470A-M |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 100 | 201000001537 | Corrective |
| 30 Sept 2026 | 1,000 | 203000029840 | Turnaround |
| 29 Sept 2026 | 1,000 | 201000002157 | Corrective |
| 29 Sept 2026 | 500 | 201000026148 | Corrective |
| 27 Sept 2026 | 200 | 201000013019 | Corrective |
| 27 Sept 2026 | 500 | 209000029477 | Other maintenance |
| 25 Sept 2026 | 50 | 201000028026 | Corrective |
| 24 Sept 2026 | 100 | 201000023380 | Corrective |
| 24 Sept 2026 | 50 | 209000029477 | Other maintenance |
| 22 Sept 2026 | 50 | 201000037585 | Corrective |
| 20 Sept 2026 | 50 | 201000006305 | Corrective |
| 20 Sept 2026 | 200 | 201000010227 | Corrective |
| 17 Sept 2026 | 200 | 209000036917 | Other maintenance |
| 14 Sept 2026 | 100 | 201000034196 | Corrective |
| 11 Sept 2026 | 100 | 201000020312 | Corrective |