TERMINAL,LUG,PIN,1.25X6MM,CRIMP

Material 4200000289 · TERMINAL · Plant 1000

CMonitorHealthy
Material
4200000289
Category
TERMINAL
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 5 FuncLocs A/B)
Supplier
PRIMA LOGAM SENTOSA PT
Lead time
21 d · P80 22 d
Unit price
Rp 2,234

Recommendation

  • 1.Forecast 1,263 EA/year: 1,263 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~21 days; expected demand during lead time 71.
  • 3.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 396, order up to 1,660.
  • 4.ML early warning: 89% probability of demand in the next 90 days.
ML early warningLast turnaround used 5,270Single sourceAbnormal consumption
On hand / on order
663 / 0
no open PO
Today Min / Max
617 / 1,083
static parameters in BoM
Rec. Min (reorder point)
396
safety stock 326
Rec. Max
1,660
order qty 1,264
Service level
99.4%
stockout risk now 0%
Unit price
Rp 2,234
PO history
ML early warning: 89% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 68 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (5,770 units) excluded from the baseline.

Demand pattern Lumpy · 13 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 32.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~9 days.

Installed on 5 functional locations

0 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-479-M
MOTOR FOR PP-479
C130.62
PX_JBX-244D
JUNCTION BOX (EXP)
C100.01
PX_JBX-307C
JUNCTION BOX
C100.01
PX_KC-447-M
MOTOR FOR KC-447
C100.57
PY_5441-6222B-F11-A
MARSHALLING TERMINAL
C100.01

Lead time and procurement

Lead time 21 ± 16 days (PO history, 7 PO lines) · on-time 44%

PR dateTypeQtyUnit priceDeliveryLead time
19 May 2026PR03
Regular replenishment
7,237Rp 2,18901 Jun 202613 d
17 Feb 2026PR03
Regular replenishment
7,416Rp 2,19705 Mar 202616 d
25 Dec 2025PR03
Regular replenishment
6,479Rp 2,23403 Jan 20269 d
02 Dec 2025PR03
Regular replenishment
7,218Rp 2,36827 Jan 202656 d
20 Jul 2025PR03
Regular replenishment
5,817Rp 2,20125 Jul 20255 d
16 Jun 2025PR03
Regular replenishment
3,518Rp 2,36509 Jul 202523 d
06 May 2025PR03
Regular replenishment
7,416Rp 2,23726 May 202520 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jan 2026MediumPX_PP-479-MPainting PP-479-M
21 Nov 2025MediumPX_PP-479-MReplace lamp as per PM finding
22 May 2025LowPX_PP-479-MMegger test PP-479-M

Recent goods issues

Posting dateQtyOrderOrder type
25 Jul 2026100201000014397Corrective
18 Jun 2026100209000016742Other maintenance
26 May 202620201000002230Corrective
14 Feb 202620201000017413Corrective
04 Jan 202650201000023618Corrective
27 Dec 20255,000203000006078Turnaround
20 Dec 2025200203000022966Turnaround
16 Nov 2025200201000026377Corrective
13 Nov 202520203000023445Turnaround
02 Nov 202550203000039255Turnaround
01 Nov 2025200201000009148Corrective
21 Sept 2025200201000004313Corrective
27 Aug 2025500209000009999Other maintenance
22 Aug 2025500203000020904Turnaround
23 Jul 20255,000201000014364Corrective