TERMINAL,LUG,RING,5.5X3MM,CRIMP
Material 4200000319 · TERMINAL · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4200000319
- Category
- TERMINAL
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 8 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 21 d · P80 35 d
- Unit price
- Rp 2,031 (est.)
Recommendation
- 1.Forecast 227 EA/year: 227 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~21 days; expected demand during lead time 13.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 220, order up to 447.
- 4.On hand 100 + on order 0 is at or below the reorder point: order 347 now.
- 5.Installed on 8 FuncLoc(s), 5 of them criticality A/B.
- 6.Identical part 4200001273 holds spare stock: transfer 11 EA instead of buying, then buy the remaining 336.
Proposed purchase requisition
336 EA
Rp 682,416 · order by 01 Oct 2026
Expected arrival ≈ 21 days
Price estimatedLead time estimatedSame description as 1 other material number
On hand / on order
100 / 0
no open PO
Today Min / Max
17 / 45
static parameters in BoM
Rec. Min (reorder point)
220
safety stock 207
Rec. Max
447
order qty 227
Service level
100.0%
stockout risk now 11%
Unit price
Rp 2,031
Category + unit estimate
ML early warning: 19% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 37 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 398.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~9 days.
Installed on 8 functional locations
5 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1177C-M MOTOR FOR PP-1177C | A | 1 | 0 | 0.19 |
| PX_PP-1776B-M MOTOR FOR PP-1776B | A | 1 | 0 | 0.19 |
| PX_PP-1384B-CSS CONTROL SWITCH STATION FOR PP-1384B-M | B | 1 | 1 | 0.62 |
| PX_PP-1843-CSS CONTROL SWITCH STATION FOR PP-1843-M | B | 1 | 0 | 0.19 |
| PY_PP-1862B-CSS CONTROL SWITCH STATION FOR PP-1862B-M | B | 1 | 0 | 0.19 |
| PX_PP-1158-M MOTOR FOR PP-1158 | C | 1 | 3 | 1.47 |
| PX_PP-1225B-M MOTOR FOR PP-1225B | C | 1 | 1 | 0.19 |
| PX_JBX-244D JUNCTION BOX (EXP) | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 21 ± 13 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Aug 2026 | Medium | PX_PP-1158-M | Megger test PP-1158-M |
| 04 Jul 2026 | Medium | PX_PP-1158-M | Megger test PP-1158-M |
| 14 Jul 2025 | Medium | PX_PP-1158-M | Repair insulation PP-1158-M |
| 12 Jun 2025 | Medium | PX_PP-1384B-CSS | Replace lamp as per PM finding |
| 18 May 2025 | Low | PX_PP-1225B-M | PP-1225B-M bearing noise |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Aug 2026 | 200 | 201000006447 | Corrective |
| 23 Aug 2026 | 20 | 201000006447 | Corrective |