TERMINAL,LUG,FORK,1.25X3MM,CRIMP

Material 4200000926 · TERMINAL · Plant 1000

BMonitorSlow-moving
Material
4200000926
Category
TERMINAL
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 3 FuncLocs A/B)
Supplier
RAJAWALI INDUSTRI ABADI PT
Lead time
32 d · P80 35 d
Unit price
Rp 9,393

Recommendation

  • 1.Forecast 415 EA/year: 415 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~32 days; expected demand during lead time 37.
  • 3.A 96.4% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1,000.
  • 4.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Single sourceSame description as 1 other material number
On hand / on order
121 / 0
no open PO
Today Min / Max
81 / 197
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1,000
order qty 1,000
Service level
96.4%
stockout risk now 4%
Unit price
Rp 9,393
PO history
ML early warning: 27% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 371 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 20.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~9 days.

Installed on 3 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1716-M
MOTOR FOR PP-1716
B100.19
PX_PP-1107B-CSS
CONTROL SWITCH STATION FOR PP-1107B-M
C120.62
PX_PP-1701B-CSS
CONTROL SWITCH STATION FOR PP-1701B-M
C110.19

Lead time and procurement

Lead time 32 ± 13 days (PO history + category, 2 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
24 Jun 2026PR01
Import / long-lead
337Rp 9,69501 Sept 202669 d
10 Jun 2026PR03
Regular replenishment
300Rp 9,09010 Jul 202630 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
08 Dec 2025LowPX_PP-1107B-CSSInstall scaffolding at PP-1107B-CSS
25 Jul 2025MediumPX_PP-1107B-CSSReplace lamp as per PM finding
14 May 2025MediumPX_PP-1701B-CSSInstall scaffolding at PP-1701B-CSS

Recent goods issues

Posting dateQtyOrderOrder type
25 Sept 20251,000201000007115Corrective