TERMINAL,LUG,FORK,2X6MM,CRIMP
Material 4200001027 · TERMINAL · Plant 1000
ATransferCriticalStockout
- Material
- 4200001027
- Category
- TERMINAL
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 6 FuncLocs A/B)
- Supplier
- LANGIT SEJAHTERA GLOBAL PT
- Lead time
- 17 d · P80 15 d
- Unit price
- Rp 1,031
Recommendation
- 1.Forecast 40 EA/year: 40 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~17 days; expected demand during lead time 1.9.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 50, order up to 100.
- 4.On hand 0 + on order 0 is at or below the reorder point: 100 needed.
- 5.Installed on 6 FuncLoc(s), 3 of them criticality A/B.
- 6.Identical part 4200000144 holds spare stock: transfer 100 EA instead of buying — no purchase needed.
Last turnaround used 250Single sourceSame description as 1 other material number
On hand / on order
0 / 0
no open PO
Today Min / Max
185 / 368
static parameters in BoM
Rec. Min (reorder point)
50
safety stock 49
Rec. Max
100
order qty 50
Service level
99.9%
stockout risk now 4%
Unit price
Rp 1,031
PO history
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 297 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (250 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 154.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~9 days.
Installed on 6 functional locations
3 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-818-M MOTOR FOR PP-818 | A | 1 | 4 | 1.05 |
| PX_PP-1012C-M MOTOR FOR PP-1012C | A | 1 | 2 | 0.19 |
| PX_PP-1892B-CSS CONTROL SWITCH STATION FOR PP-1892B-M | A | 1 | 1 | 0.19 |
| PX_JBX-1061B JUNCTION BOX | C | 1 | 0 | 0.01 |
| PX_KC-155-M MOTOR FOR KC-155 | C | 1 | 0 | 0.57 |
| UT_PP-641A-M MOTOR FOR PP-641A | C | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 17 ± 7 days (PO history, 4 PO lines) · on-time 71%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 26 Apr 2026 | PR06 Regular replenishment | 130 | Rp 1,022 | 11 May 2026 | 15 d |
| 10 Feb 2026 | PR06 Regular replenishment | 91 | Rp 1,039 | 23 Feb 2026 | 13 d |
| 17 Oct 2025 | PR06 Regular replenishment | 75 | Rp 1,010 | 02 Nov 2025 | 16 d |
| 16 Jun 2025 | PR03 Regular replenishment | 140 | Rp 1,073 | 30 Jun 2025 | 14 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 07 Sept 2026 | Low | PX_PP-1012C-M | Install scaffolding at PP-1012C-M |
| 09 Apr 2026 | Medium | PX_PP-818-M | Install scaffolding at PP-818-M |
| 19 Mar 2026 | Medium | PX_PP-818-M | Leak from packing |
| 25 Sept 2025 | Medium | PX_PP-818-M | PP-818-M bearing noise |
| 23 May 2025 | Low | PX_PP-818-M | PP-818-M high temp |
| 14 May 2025 | Medium | PX_PP-1892B-CSS | Leak from packing |
| 04 May 2025 | Medium | PX_PP-1012C-M | PSM25/Megger test PP-1012C-M |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Dec 2025 | 50 | 201000023766 | Corrective |
| 07 Dec 2025 | 100 | 203000014228 | Turnaround |
| 06 Dec 2025 | 100 | 203000014228 | Turnaround |
| 03 Dec 2025 | 50 | 203000014228 | Turnaround |