GLAND,CABLE,SIZE NF34,PTFE
Material 4200001348 · GLAND · Plant 1000
AReduceExcess
- Material
- 4200001348
- Category
- GLAND
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (15 of 38 FuncLocs A/B)
- Supplier
- PRIMA LOGAM SENTOSA PT
- Lead time
- 32 d · P80 46 d
- Unit price
- Rp 51,972
Recommendation
- 1.Forecast 11 EA/year: 11 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~32 days; expected demand during lead time 0.9.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 18.
- 4.Stock 29 exceeds the level to keep (18) by 11.
- 5.Installed on 38 FuncLoc(s), 15 of them criticality A/B.
- 6.ML early warning: 90% probability of demand in the next 90 days.
ML early warningSingle source
On hand / on order
29 / 0
no open PO
Today Min / Max
6 / 18
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 7
Rec. Max
18
order qty 11
Service level
100.0%
stockout risk now 0%
Unit price
Rp 51,972
PO history
ML early warning: 90% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 64 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (4 units) excluded from the baseline.
Demand pattern Intermittent · 11 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~16 days.
Installed on 38 functional locations
15 with criticality A/B · 53 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-818-M MOTOR FOR PP-818 | A | 1 | 4 | 1.05 |
| PX_PIT-1663 PRESSURE | A | 1 | 1 | 0.04 |
| PX_FIT-1454C HE-536 INLET FLOW | A | 1 | 0 | 0.04 |
| PX_PP-1740B-M MOTOR FOR PP-1740B | A | 1 | 0 | 0.19 |
| PX_PP-473B-CSS CONTROL SWITCH STATION FOR PP-473B-M | A | 2 | 0 | 0.19 |
| PX_PP-752B-M MOTOR FOR PP-752B | A | 1 | 0 | 0.19 |
| PX_TEL-1452-37A PP-1325 BTM | A | 1 | 0 | 0.01 |
| PX_TIT-992A TEMPERATURE | A | 1 | 0 | 0.04 |
| PX_DPT-808A CL-121 DP | B | 3 | 3 | 0.49 |
| PX_PP-1701B-M MOTOR FOR PP-1701B | B | 1 | 2 | 0.62 |
| PX_TEL-389-47A TEMPERATURE | B | 4 | 2 | 0.44 |
| PX_TEL-1827 CRACKED GAS OUTLET BF-111 | B | 1 | 1 | 0.44 |
Lead time and procurement
Lead time 32 ± 18 days (PO history, 7 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 21 Jun 2026 | PR03 Regular replenishment | 6 | Rp 52,234 | 28 Aug 2026 | 68 d |
| 20 Apr 2026 | PR03 Regular replenishment | 5 | Rp 51,972 | 08 May 2026 | 18 d |
| 19 Feb 2026 | PR03 Regular replenishment | 3 | Rp 51,078 | 07 Mar 2026 | 16 d |
| 01 Sept 2025 | PR03 Regular replenishment | 4 | Rp 53,339 | 07 Oct 2025 | 36 d |
| 30 Aug 2025 | PR06 Regular replenishment | 10 | Rp 50,966 | 27 Sept 2025 | 28 d |
| 16 Jul 2025 | PR03 Regular replenishment | 7 | Rp 50,869 | 06 Aug 2025 | 21 d |
| 09 Jul 2025 | PR03 Regular replenishment | 11 | Rp 53,408 | 26 Aug 2025 | 48 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 04 Sept 2026 | Medium | PX_TEL-389-47A | Install scaffolding at TEL-389-47A |
| 09 Apr 2026 | Medium | PX_PP-818-M | Install scaffolding at PP-818-M |
| 19 Mar 2026 | Medium | PX_PP-818-M | Leak from packing |
| 10 Mar 2026 | Medium | PX_DPT-808A | Leak from packing |
| 06 Jan 2026 | Low | PX_PP-1701B-M | PP-1701B-M bearing noise |
| 24 Dec 2025 | Medium | PX_DPT-808A | Install scaffolding at DPT-808A |
| 25 Sept 2025 | Medium | PX_PP-818-M | PP-818-M bearing noise |
| 07 Jul 2025 | Low | PY_JBX-899 | Install scaffolding at JBX-899 |
| 25 Jun 2025 | Medium | PX_TEL-389-47A | PSM25/[MSI-B-25-NKN-289/M] Replace line |
| 14 Jun 2025 | Medium | PX_TEL-1827 | Inspection TEL-1827.ok |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 29 Jul 2026 | 1 | 201000004503 | Corrective |
| 12 Jun 2026 | 2 | 201000018636 | Corrective |
| 13 May 2026 | 1 | 201000021126 | Corrective |
| 22 Mar 2026 | 1 | 201000019772 | Corrective |
| 16 Mar 2026 | 3 | 201000023383 | Corrective |
| 31 Jan 2026 | 2 | 201000034265 | Corrective |
| 11 Dec 2025 | 1 | 201000019124 | Corrective |
| 04 Oct 2025 | 3 | 201000017536 | Corrective |
| 26 Aug 2025 | 1 | 203000020904 | Turnaround |
| 25 Aug 2025 | 1 | 203000020904 | Turnaround |
| 24 Aug 2025 | 1 | 203000020904 | Turnaround |
| 21 Aug 2025 | 1 | 203000020904 | Turnaround |
| 19 Aug 2025 | 1 | 201000004327 | Corrective |
| 03 Jul 2025 | 1 | 201000021723 | Corrective |
| 21 Jun 2025 | 2 | 204000028641 | Preventive |