GLAND,CABLE,MODEL PI295,VITON

Material 4200001389 · GLAND · Plant 1000

AReorderNormalSlow-moving
Material
4200001389
Category
GLAND
Base unit
EA
MRP type
Stock Item
Criticality
A (12 of 25 FuncLocs A/B)
Supplier
No PO history
Lead time
29 d · P80 52 d
Unit price
Rp 183,915 (est.)

Recommendation

  • 1.Forecast 2.4 EA/year: 2.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~29 days; expected demand during lead time 0.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 4 now.
  • 5.Installed on 25 FuncLoc(s), 12 of them criticality A/B.
  • 6.ML early warning: 39% probability of demand in the next 90 days.
Proposed purchase requisition
4 EA
Rp 735,660 · order by 01 Oct 2026
Expected arrival ≈ 29 days
ML early warningPrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.9%
stockout risk now 1%
Unit price
Rp 183,915
Category + unit estimate
ML early warning: 39% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 278 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 690.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~16 days.

Installed on 25 functional locations

12 with criticality A/B · 28 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-278
FLOW
A110.47
PX_TIT-556A
TEMPERATURE
A110.47
PX_JBX-1777A
JUNCTION BOX
A100.01
PX_PIT-1377
COOLING WATER PRESSURE
A100.04
PX_TIT-790C-10A
TEMPERATURE
A100.04
PY_PP-1139B-M
MOTOR FOR PP-1139B
B110.19
PX_JBX-1547C
JUNCTION BOX (EXP)
B100.01
PX_PP-1540-M
MOTOR FOR PP-1540
B100.19
PX_PP-1991A-M
MOTOR FOR PP-1991A
B100.19
PX_PP-795D-M
MOTOR FOR PP-795D
B100.19
PX_TEL-117C-4
TEMPERATURE
B100.01
PX_TEL-1364
KC-391D BTM
B100.01

Lead time and procurement

Lead time 29 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
05 Sept 2026MediumPX_JBX-1039C[MSI-B-26-RWD-296] Permanent repair
19 Dec 2025MediumPX_JBX-1039CReplace gland JBX-1039C
15 Aug 2025MediumPX_TIT-556A[MSI-B-25-FTU-227] Permanent repair
25 Jun 2025LowPX_FIT-278Check FIT-278.ok
21 May 2025LowPX_JBX-1039CJBX-1039C water ingress
08 May 2025MediumPY_PP-1139B-MInstall scaffolding at PP-1139B-M

Recent goods issues

Posting dateQtyOrderOrder type
27 Dec 20252201000019016Corrective
16 Nov 20251201000014817Corrective
15 Oct 20251204000026329Preventive
14 Oct 20251204000026329Preventive
19 May 20251201000022774Corrective