LAMP,LED,9W,24VDC,FLOOD

Material 4200004986 · LAMP · Plant 1000

BReduceNon-moving
Material
4200004986
Category
LAMP
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
41 d · P80 60 d
Unit price
Rp 403,312 (est.)

Recommendation

  • 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~41 days; expected demand during lead time 0.0.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 4.Stock 116 exceeds the level to keep (2) by 114.
  • 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
116 / 0
no open PO
Today Min / Max
4 / 12
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
99.7%
stockout risk now 0%
Unit price
Rp 403,312
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~19 days.

Installed on 3 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-390B-CSS
CONTROL SWITCH STATION FOR PP-390B-M
B100.19
PX_PP-217-CSS
CONTROL SWITCH STATION FOR PP-217-M
C100.19
PY_PP-490-CSS
CONTROL SWITCH STATION FOR PP-490-M
C100.19

Lead time and procurement

Lead time 41 ± 24 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Never issued in the 17-month history.