FAN,COOLING MOTOR,TYPE OI508,VITON
Material 4200006682 · FAN · Plant 1000
BLong-leadReorderCriticalStockout
- Material
- 4200006682
- Category
- FAN
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- B (1 of 1 FuncLocs A/B)
- Supplier
- DUTA ENERGI INTERNASIONAL PT
- Lead time
- 53 d · P80 103 d
- Unit price
- Rp 1.5M
Recommendation
- 1.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~53 days; expected demand during lead time 0.1.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
- 5.Long lead time: 80% of deliveries took up to 103 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 6.0M · order by 01 Oct 2026
Expected arrival ≈ 53 days
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
100.0%
stockout risk now 14%
Unit price
Rp 1.5M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 258 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 148.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~27 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-402A-M MOTOR FOR PP-402A | B | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 53 ± 31 days (PO history + category, 2 PO lines) · on-time 50%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Nov 2025 | PR06 Regular replenishment | 2 | Rp 1.5M | 27 Dec 2025 | 44 d |
| 20 Sept 2025 | PR06 Regular replenishment | 2 | Rp 1.5M | 17 Oct 2025 | 27 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 16 Jan 2026 | 1 | 201000037819 | Corrective |
| 08 Dec 2025 | 1 | 201000034802 | Corrective |
| 07 Dec 2025 | 1 | 201000034802 | Corrective |