Sparely
DU

FAN,COOLING MOTOR,MODEL FH56,INCOLOY

Material 4200007390 · FAN · Plant 1000

ALong-leadReduceExcess
Material
4200007390
Category
FAN
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
BINTANG SUPLINDO GLOBAL PT
Lead time
68 d · P80 103 d
Unit price
Rp 814,002

Recommendation

  • 1.Forecast 0.6 EA/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~68 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 6 exceeds the level to keep (3) by 3.
  • 5.Long lead time: 80% of deliveries took up to 103 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
6 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 814,002
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 92 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 324.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1733A-M
MOTOR FOR PP-1733A
A120.62

Lead time and procurement

Lead time 68 ± 31 days (PO history + category, 1 PO lines) · on-time 29%

PR dateTypeQtyUnit priceDeliveryLead time
19 Oct 2025PR06
Regular replenishment
2Rp 814,00205 Jan 202678 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
07 Jul 2026MediumPX_PP-1733A-MMegger test PP-1733A-M
22 May 2025LowPX_PP-1733A-MPP-1733A-M bearing noise

Recent goods issues

Posting dateQtyOrderOrder type
01 Jul 20261201000017983Corrective