CABLE,INSTRUMENT,1PR X 0.75MM2,ARMOURED
Material 4200008195 · CABLE · Plant 1000
BLong-leadMonitorCritical insurance spare
- Material
- 4200008195
- Category
- CABLE
- Base unit
- M
- MRP type
- Stock Item
- Criticality
- B (2 of 9 FuncLocs A/B)
- Supplier
- RAJAWALI INDUSTRI ABADI PT
- Lead time
- 67 d · P80 140 d
- Unit price
- Rp 27,891
Recommendation
- 1.Forecast 1.0 M/year: 1.0 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~67 days; expected demand during lead time 0.2.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 50.
- 4.No issue in 17 months, but it protects critical equipment: keep it.
- 5.Long lead time: 80% of deliveries took up to 140 days and the fastest seen in its category 21 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 9 FuncLoc(s), 2 of them criticality A/B.
- 7.ML early warning: 35% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceSame description as 2 other material numbers
On hand / on order
13 / 0
no open PO
Today Min / Max
5 / 15
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
50
order qty 50
Service level
99.6%
stockout risk now 0%
Unit price
Rp 27,891
PO history
ML early warning: 35% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~21 days.
Installed on 9 functional locations
2 with criticality A/B · 46.8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_JBX-486A JUNCTION BOX | B | 5 | 1 | 0.01 |
| PX_JBX-1811 JUNCTION BOX (EXP) | B | 25 | 0 | 0.01 |
| PX_JBX-1784A JUNCTION BOX | C | 5 | 1 | 0.44 |
| PX_JBX-1842A JUNCTION BOX | C | 0.5 | 0 | 0.01 |
| PX_JBX-324 JUNCTION BOX | C | 5 | 0 | 0.01 |
| PX_JBX-666B JUNCTION BOX | C | 0.5 | 0 | 0.01 |
| PX_JBX-828A JUNCTION BOX | C | 0.32 | 0 | 0.01 |
| PY_1129-1016A-F26-B SPENT CAUSTIC LINE | C | 5 | 0 | 0.01 |
| PY_JBX-955C JUNCTION BOX | S | 0.5 | 0 | 0.01 |
Lead time and procurement
Lead time 67 ± 55 days (PO history, 3 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 05 Jun 2026 | PR04 Regular (other) | 2 | Rp 27,891 | 07 Aug 2026 | 63 d |
| 11 Sept 2025 | PR06 Regular replenishment | 2 | Rp 28,393 | 14 Oct 2025 | 33 d |
| 15 May 2025 | PR03 Regular replenishment | 2 | Rp 27,196 | 22 Nov 2025 | 191 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 07 Aug 2025 | Medium | PX_JBX-1784A | Leak from packing |
| 12 May 2025 | Medium | PX_JBX-486A | Replace lamp as per PM finding |
Recent goods issues
Never issued in the 17-month history.