FAN,COOLING MOTOR,DWG.746-2032,FOR KC-37
Material 4200010704 · FAN · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4200010704
- Category
- FAN
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- PRIMA LOGAM SENTOSA PT
- Lead time
- 85 d · P80 114 d
- Unit price
- Rp 2.6M
Recommendation
- 1.Forecast 3.4 EA/year: 3.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~85 days; expected demand during lead time 0.8.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 10.
- 4.On hand 0 + on order 3 is at or below the reorder point: order 7 now.
- 5.Long lead time: 80% of deliveries took up to 114 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
7 EA
Rp 17.9M · order by 01 Oct 2026
Expected arrival ≈ 85 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 3
next delivery 02 May 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
10
order qty 4
Service level
99.9%
stockout risk now 6%
Unit price
Rp 2.6M
PO history
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 157 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 981.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-371B-M MOTOR FOR KC-371B | A | 1 | 0 | 0.57 |
Lead time and procurement
Lead time 85 ± 26 days (PO history, 4 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 Apr 2026 | PR06 Regular replenishment | 3 | Rp 2.5M | 02 May 2027 open | 381 d |
| 19 Mar 2026 | PR06 Regular replenishment | 2 | Rp 2.6M | 02 Jul 2026 | 105 d |
| 16 Mar 2026 | PR06 Regular replenishment | 2 | Rp 2.6M | 21 Jun 2026 | 97 d |
| 26 Oct 2025 | PR06 Regular replenishment | 2 | Rp 2.5M | 03 Mar 2026 | 128 d |
| 04 Sept 2025 | PR10 Other | 3 | Rp 2.6M | 16 Nov 2025 | 73 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 27 Apr 2026 | 1 | 201000012822 | Corrective |
| 26 Apr 2026 | 3 | 201000012822 | Corrective |
| 22 Apr 2026 | 2 | 201000036349 | Corrective |