FAN,COOLING MOTOR,DWG.746-2032,FOR KC-37

Material 4200010704 · FAN · Plant 1000

ALong-leadReorderCriticalStockout
Material
4200010704
Category
FAN
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
PRIMA LOGAM SENTOSA PT
Lead time
85 d · P80 114 d
Unit price
Rp 2.6M

Recommendation

  • 1.Forecast 3.4 EA/year: 3.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~85 days; expected demand during lead time 0.8.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 10.
  • 4.On hand 0 + on order 3 is at or below the reorder point: order 7 now.
  • 5.Long lead time: 80% of deliveries took up to 114 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
7 EA
Rp 17.9M · order by 01 Oct 2026
Expected arrival ≈ 85 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 3
next delivery 02 May 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
10
order qty 4
Service level
99.9%
stockout risk now 6%
Unit price
Rp 2.6M
PO history
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 157 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 981.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-371B-M
MOTOR FOR KC-371B
A100.57

Lead time and procurement

Lead time 85 ± 26 days (PO history, 4 PO lines) · on-time 44%

PR dateTypeQtyUnit priceDeliveryLead time
16 Apr 2026PR06
Regular replenishment
3Rp 2.5M02 May 2027
open
381 d
19 Mar 2026PR06
Regular replenishment
2Rp 2.6M02 Jul 2026105 d
16 Mar 2026PR06
Regular replenishment
2Rp 2.6M21 Jun 202697 d
26 Oct 2025PR06
Regular replenishment
2Rp 2.5M03 Mar 2026128 d
04 Sept 2025PR10
Other
3Rp 2.6M16 Nov 202573 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
27 Apr 20261201000012822Corrective
26 Apr 20263201000012822Corrective
22 Apr 20262201000036349Corrective