Sparely
DU

RING,WEAR,DWG.981-4465,FOR PP-1250

Material 4300000166 · RING · Plant 1000

AReorderCriticalStockout
Material
4300000166
Category
RING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
92 d · P80 143 d
Unit price
Rp 8.2M (est.)

Recommendation

  • 1.Forecast 0.8 EA/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~92 days; expected demand during lead time 0.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 2 now.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
2 EA
Rp 16.4M · order by 01 Oct 2026
Expected arrival ≈ 92 days
Convert to Stock ItemPrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
100.0%
stockout risk now 2%
Unit price
Rp 8.2M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 97.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~59 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1250
METHANE PUMP
A141.90

Lead time and procurement

Lead time 92 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Feb 2027PX_PP-1250Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Dec 2025LowPX_PP-1250PP-1250 high vibration
16 Nov 2025HighPX_PP-1250Leak from packing
20 Oct 2025LowPX_PP-1250PP-1250 seal leak
20 Jun 2025MediumPX_PP-1250PP-1250 seal leak

Recent goods issues

Never issued in the 17-month history.