BLADE,ROTOR,DWG.726-8864,FOR KT-202
Material 4300000389 · BLADE · Plant 1000
SReduceExcess
- Material
- 4300000389
- Category
- BLADE
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- S (0 of 1 FuncLocs A/B)
- Supplier
- RAJAWALI REFRAKTORI PRATAMA PT
- Lead time
- 181 d · P80 263 d
- Unit price
- Rp 189.3M
Recommendation
- 1.Forecast 2.4 SET/year: 2.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~181 days; expected demand during lead time 1.2.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Stock 10 exceeds the level to keep (0) by 10.
Single sourceOpen POLead time estimated
On hand / on order
10 / 1
next delivery 17 Oct 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 189.3M
PO history
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 87 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~99 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
Lead time and procurement
Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Oct 2025 | PR01 Import / long-lead | 1 | Rp 189.3M | 17 Oct 2027 open | 725 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 09 Jan 2026 | Medium | PX_KT-202 | KT-202 governor valve hunting |
| 17 Sept 2025 | Medium | PX_KT-202 | Replace lamp as per PM finding |
| 06 Jul 2025 | Low | PX_KT-202 | KT-202 steam leak at gland |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 06 Jul 2026 | 2 | 201000014051 | Corrective |