SEAL,LABYRINTH,DWG.907-7279,FOR KT-202
Material 4300000816 · SEAL · Plant 1000
SMaintainNo stock needed
- Material
- 4300000816
- Category
- SEAL
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- S (0 of 1 FuncLocs A/B)
- Supplier
- PERMATA SUPLINDO JAYA PT
- Lead time
- 146 d · P80 213 d
- Unit price
- Rp 129.5M
Recommendation
- 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~146 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Single sourceOpen PO
On hand / on order
0 / 1
next delivery 17 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 129.5M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 389,340/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~71 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
Lead time and procurement
Lead time 146 ± 65 days (PO history + category, 1 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 07 Jun 2026 | PR06 Regular replenishment | 1 | Rp 129.5M | 17 Oct 2026 open | 132 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 09 Jan 2026 | Medium | PX_KT-202 | KT-202 governor valve hunting |
| 17 Sept 2025 | Medium | PX_KT-202 | Replace lamp as per PM finding |
| 06 Jul 2025 | Low | PX_KT-202 | KT-202 steam leak at gland |
Recent goods issues
Never issued in the 17-month history.