BEARING,JOURNAL,DWG.330-5509,FOR KT-397A
Material 4300003902 · BEARING · Plant 1000
ALong-leadMaintainNo stock needed
- Material
- 4300003902
- Category
- BEARING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- RAJAWALI REFRAKTORI PRATAMA PT
- Lead time
- 136 d · P80 127 d
- Unit price
- Rp 673.9M
Recommendation
- 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~136 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 07 Jan 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 673.9M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 56.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
Lead time and procurement
Lead time 136 ± 40 days (PO history + category, 2 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 01 Jun 2026 | PR03 Regular replenishment | 1 | Rp 672.9M | 07 Jan 2027 open | 220 d |
| 09 Oct 2025 | PR06 Regular replenishment | 2 | Rp 674.9M | 01 Aug 2026 | 296 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
| 14 May 2026 | Low | PX_KT-397A | KT-397A trip test |
| 02 Apr 2026 | Medium | PX_KT-397A | Follow up after steam upset KT-397A |
| 10 May 2025 | Medium | PX_KT-397A | Leak from packing |
Recent goods issues
Never issued in the 17-month history.