Sparely
DU

SEAT RING,VALVE,DWG.473-1978,FOR FCV-638

Material 4300006657 · SEAT RING · Plant 1000

CMaintainNo stock needed
Material
4300006657
Category
SEAT RING
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
TIRTA SEJAHTERA PERSADA PT
Lead time
109 d · P80 139 d
Unit price
Rp 13.2M

Recommendation

  • 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~109 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Convert to Non StockSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 1%
Unit price
Rp 13.2M
PO history
ML early warning: 17% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (2 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 602,186/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~65 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-638
BY PASS LINE
C120.54

Lead time and procurement

Lead time 109 ± 62 days (PO history, 3 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
29 May 2026PR03
Regular replenishment
2Rp 12.9M09 Aug 202672 d
24 Jan 2026PR03
Regular replenishment
2Rp 13.2M30 Mar 202665 d
06 May 2025PR01
Import / long-lead
1Rp 13.6M06 Nov 2025184 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026MediumPX_FCV-638Replace lamp as per PM finding
01 Jun 2025MediumPX_FCV-638Painting FCV-638

Recent goods issues

Posting dateQtyOrderOrder type
28 Apr 20261203000034130Turnaround
24 Apr 20261203000034130Turnaround