SEAT RING,VALVE,DWG.473-1978,FOR FCV-638
Material 4300006657 · SEAT RING · Plant 1000
CMaintainNo stock needed
- Material
- 4300006657
- Category
- SEAT RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- TIRTA SEJAHTERA PERSADA PT
- Lead time
- 109 d · P80 139 d
- Unit price
- Rp 13.2M
Recommendation
- 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~109 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Convert to Non StockSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 1%
Unit price
Rp 13.2M
PO history
ML early warning: 17% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (2 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 602,186/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~65 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-638 BY PASS LINE | C | 1 | 2 | 0.54 |
Lead time and procurement
Lead time 109 ± 62 days (PO history, 3 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 29 May 2026 | PR03 Regular replenishment | 2 | Rp 12.9M | 09 Aug 2026 | 72 d |
| 24 Jan 2026 | PR03 Regular replenishment | 2 | Rp 13.2M | 30 Mar 2026 | 65 d |
| 06 May 2025 | PR01 Import / long-lead | 1 | Rp 13.6M | 06 Nov 2025 | 184 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_FCV-638 | Replace lamp as per PM finding |
| 01 Jun 2025 | Medium | PX_FCV-638 | Painting FCV-638 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 28 Apr 2026 | 1 | 203000034130 | Turnaround |
| 24 Apr 2026 | 1 | 203000034130 | Turnaround |