Sparely
DU

THERMOWELL,DWG.933-5504,FOR TEL-1080

Material 4300007377 · THERMOWELL · Plant 1000

SMonitorNo stock needed
Material
4300007377
Category
THERMOWELL
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
ANUGRAH TEKNOLOGI INTERNASIONAL PT
Lead time
94 d · P80 144 d
Unit price
Rp 7.1M

Recommendation

  • 1.Forecast 2.0 EA/year: 2.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~94 days; expected demand during lead time 0.5.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Single sourceOpen PO
On hand / on order
0 / 6
next delivery 07 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 1%
Unit price
Rp 7.1M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 182 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~43 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-1080
TEMPERATURE
S100.01

Lead time and procurement

Lead time 94 ± 76 days (PO history, 4 PO lines) · on-time 23%

PR dateTypeQtyUnit priceDeliveryLead time
02 Sept 2026PR03
Regular replenishment
3Rp 7.0M07 Nov 2026
open
66 d
15 Jul 2026PR01
Import / long-lead
3Rp 7.1M02 Apr 2027
open
261 d
02 Jun 2026PR03
Regular replenishment
1Rp 7.2M26 Jul 202654 d
08 Mar 2026PR06
Regular replenishment
1Rp 7.3M20 Apr 202643 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
02 Apr 20262201000020555Corrective
24 Jul 20252205000036740Other maintenance
24 Jul 20253205000036740Other maintenance
Sparely