RING,WEAR,DWG.452-6414,FOR PP-1821

Material 4300007714 · RING · Plant 1000

AReduceSlow-moving
Material
4300007714
Category
RING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
92 d · P80 143 d
Unit price
Rp 8.2M (est.)

Recommendation

  • 1.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~92 days; expected demand during lead time 0.1.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Stock 3 exceeds the level to keep (2) by 1.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 8.2M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 221 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 357.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~59 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1821
CAUSTIC PUMP
A100.19

Lead time and procurement

Lead time 92 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
22 Feb 20261201000028512Corrective