COUPLING,DWG.924-8394,FOR KC-527
Material 4300007887 · COUPLING · Plant 1000
- Material
- 4300007887
- Category
- COUPLING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 86 d · P80 139 d
- Unit price
- Rp 8.6M (est.)
Recommendation
- 1.Forecast 1.1 SET/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~86 days; expected demand during lead time 0.3.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 335.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-527 METHANOL BLOWER | A | 1 | 0 | 0.57 |
Lead time and procurement
Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 11 Jan 2026 | 3 | 204000006058 | Preventive |