SEAL,LABYRINTH,DWG.989-4187,FOR KC-391D
Material 4300008448 · SEAL · Plant 1000
ALong-leadReduceSlow-moving
- Material
- 4300008448
- Category
- SEAL
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- PERMATA INSTRUMEN MAKMUR PT
- Lead time
- 179 d · P80 213 d
- Unit price
- Rp 85.1M
Recommendation
- 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~179 days; expected demand during lead time 0.0.
- 3.A 97.2% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Stock 2 exceeds the level to keep (1) by 1.
- 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadLast turnaround used 1Single sourceOpen PO
On hand / on order
2 / 3
next delivery 12 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
97.2%
stockout risk now 0%
Unit price
Rp 85.1M
PO history
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 87.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-391D QUENCH WATER COMPRESSOR | A | 1 | 2 | 1.43 |
Lead time and procurement
Lead time 179 ± 65 days (PO history + category, 1 PO lines) · on-time 40%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 23 Mar 2026 | PR06 Regular replenishment | 1 | Rp 86.2M | 12 Dec 2026 open | 264 d |
| 25 Jul 2025 | PR05 Project / turnaround | 2 | Rp 84.1M | 03 Feb 2027 open | 558 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 Dec 2025 | Low | PX_KC-391D | Leak from packing |
| 18 Jul 2025 | High | PX_KC-391D | KC-391D high vibration |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 28 Dec 2025 | 1 | 203000006078 | Turnaround |