Sparely
DU

POSITIONER,VALVE,DWG.659-5969,FOR TCV-14

Material 4300009432 · POSITIONER · Plant 1000

CReduceSlow-moving
Material
4300009432
Category
POSITIONER
Base unit
EA
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
118 d · P80 166 d
Unit price
Rp 32.5M

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~118 days; expected demand during lead time 0.1.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 1 exceeds the level to keep (0) by 1.
Single sourceOpen PO
On hand / on order
1 / 4
next delivery 21 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 32.5M
PO history
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 485 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~40 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-1407
TEMPERATURE CONTROL VALVE
C110.12

Lead time and procurement

Lead time 118 ± 64 days (PO history + category, 2 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
11 Aug 2026PR06
Regular replenishment
2Rp 33.1M21 Oct 2026
open
71 d
10 May 2026PR01
Import / long-lead
2Rp 31.9M30 Dec 2026
open
234 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 May 2025LowPX_TCV-1407Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
03 Jun 20252201000025970Corrective
24 May 20251204000036327Preventive