TRIM SET,CONTROL VALVE,DWG.647-1416,FOR

Material 4300009511 · TRIM SET · Plant 1000

CMonitorStockout
Material
4300009511
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
GUNUNG PERKASA NUSANTARA PT
Lead time
170 d · P80 236 d
Unit price
Rp 54.2M

Recommendation

  • 1.Forecast 1.3 SET/year: 0.5 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~170 days; expected demand during lead time 1.0 (incl. 0.7 planned).
  • 3.A 77.6% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
Convert to Stock ItemSingle sourceOpen POPlanned demand in lead time
On hand / on order
0 / 2
next delivery 07 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
77.6%
stockout risk now 3%
Unit price
Rp 54.2M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 184 days ago, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 17.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~75 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-274A
HE-1596B OUTLET FLOW
C130.96

Lead time and procurement

Lead time 170 ± 83 days (PO history + category, 1 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
18 May 2026PR06
Regular replenishment
2Rp 54.2M07 Dec 2026
open
203 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
09 Dec 2026PX_FCV-274AFinal Element Overhaul; Control Valve0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Aug 2026MediumPX_FCV-274AFCV-274A; IA leak from regulator
14 Oct 2025MediumPX_FCV-274AFCV-274A; IA leak from regulator
25 May 2025LowPX_FCV-274AFCV-274A passing

Recent goods issues

Posting dateQtyOrderOrder type
31 Mar 20261201000037731Corrective