SPRING,SAFETY VALVE,DWG.909-2380,FOR PRV
Material 4300009876 · SPRING · Plant 1000
- Material
- 4300009876
- Category
- SPRING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- S (0 of 1 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 137 d · P80 196 d
- Unit price
- Rp 8.8M (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 0.6 EA/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~137 days; expected demand during lead time 0.2.
- 4.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
- 5.Stock 6 exceeds the level to keep (4) by 2.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 495.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PRV-193 SAFETY VALVE HE-1468A | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 137 ± 65 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Apr 2026 | 2 | 201000002804 | Corrective |