DU

IMPELLER,DWG.576-5986,FOR PP-278

Material 4300010213 · IMPELLER · Plant 1000

AMaintainHealthy
Material
4300010213
Category
IMPELLER
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
184 d · P80 276 d
Unit price
Rp 102.1M (est.)

Recommendation

  • 1.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~184 days; expected demand during lead time 0.5.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
  • 4.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 144 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-278
FEED PUMP
A162.33

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
09 May 2026MediumPX_PP-278PP-278 seal leak
04 May 2026MediumPX_PP-278Replace bearing PP-278
09 Feb 2026LowPX_PP-278Replace lamp as per PM finding
19 Oct 2025LowPX_PP-278PP-278 discharge pressure low
03 Oct 2025MediumPX_PP-278PP-278 abnormal noise
10 May 2025MediumPX_PP-278Replace bearing PP-278

Recent goods issues

Posting dateQtyOrderOrder type
10 May 20261201000007735Corrective