VALVE,GOVERNOR,DWG.768-6728,FOR KT-383A
Material 4300012075 · VALVE · Plant 1000
SMaintainNo stock needed
- Material
- 4300012075
- Category
- VALVE
- Base unit
- ASS
- MRP type
- Non Stock
- Criticality
- S (0 of 1 FuncLocs A/B)
- Supplier
- PERMATA SUPLINDO JAYA PT
- Lead time
- 77 d · P80 92 d
- Unit price
- Rp 466.7M
Recommendation
- 1.Forecast 0.2 ASS/year: 0.2 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~77 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Single sourceOpen PO
On hand / on order
0 / 2
next delivery 01 Feb 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 466.7M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 304,968/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~20 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
Lead time and procurement
Lead time 77 ± 30 days (PO history + category, 1 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 19 Aug 2026 | PR06 Regular replenishment | 2 | Rp 466.7M | 01 Feb 2027 open | 166 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 23 Jun 2025 | Medium | PX_KT-383A | KT-383A governor valve hunting |
Recent goods issues
Never issued in the 17-month history.