TRIM SET,CONTROL VALVE,DWG.716-1068,FOR
Material 4300012470 · TRIM SET · Plant 1000
- Material
- 4300012470
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 159 d · P80 236 d
- Unit price
- Rp 78.5M (est.)
Recommendation
- 1.Forecast 0.2 SET/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~159 days; expected demand during lead time 0.1.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~75 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1456A BY PASS LINE | C | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 159 ± 83 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 20 Oct 2025 | 1 | 201000008534 | Corrective |