COUPLING,DWG.127-2227,FOR PP-615A

Material 4300014305 · COUPLING · Plant 1000

BLong-leadMonitorSlow-moving
Material
4300014305
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
RAJAWALI PERKASA JAYA PT
Lead time
96 d · P80 139 d
Unit price
Rp 11.0M

Recommendation

  • 1.Forecast 1.4 SET/year: 0.7 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~96 days; expected demand during lead time 0.9 (incl. 0.7 planned).
  • 3.A 94.0% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 4.
  • 4.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadConvert to Stock ItemSingle sourceOpen POPlanned demand in lead time
On hand / on order
4 / 1
next delivery 10 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
4
order qty 3
Service level
94.0%
stockout risk now 0%
Unit price
Rp 11.0M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 283 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 55.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~44 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-615A
PROPYLENE PUMP
B100.19

Lead time and procurement

Lead time 96 ± 54 days (PO history + category, 1 PO lines) · on-time 15%

PR dateTypeQtyUnit priceDeliveryLead time
07 Jul 2026PR06
Regular replenishment
1Rp 11.0M10 Nov 2026
open
126 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Jan 2027PX_PP-615APump overhaul0.72

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
22 Dec 20253201000007382Corrective