SLEEVE,SHAFT,DWG.456-9747,FOR PP-1448B

Material 4300015164 · SLEEVE · Plant 1000

BLong-leadReduceSlow-moving
Material
4300015164
Category
SLEEVE
Base unit
EA
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
125 d · P80 210 d
Unit price
Rp 12.9M

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~125 days; expected demand during lead time 0.1.
  • 3.A 99.1% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Stock 30 exceeds the level to keep (2) by 28.
  • 5.Long lead time: 80% of deliveries took up to 210 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
30 / 5
next delivery 03 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.1%
stockout risk now 0%
Unit price
Rp 12.9M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 228 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 144.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~67 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1448B
ETHYLENE PUMP
B110.62

Lead time and procurement

Lead time 125 ± 55 days (PO history + category, 2 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
15 Aug 2026PR05
Project / turnaround
2Rp 12.5M29 Jan 2027
open
167 d
09 Aug 2026PR06
Regular replenishment
1Rp 13.4M03 Oct 2026
open
55 d
27 Feb 2026PR01
Import / long-lead
2Rp 12.9M23 Apr 2028
open
786 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Jun 2025MediumPX_PP-1448BPP-1448B abnormal noise

Recent goods issues

Posting dateQtyOrderOrder type
15 Feb 20261201000026885Corrective