COUPLING,DWG.363-2165,FOR PP-506A

Material 4300015347 · COUPLING · Plant 1000

ALong-leadReorderCriticalStockout
Material
4300015347
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
LANGIT INDUSTRI PRATAMA PT
Lead time
88 d · P80 139 d
Unit price
Rp 4.3M

Recommendation

  • 1.Forecast 2.9 SET/year: 2.9 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~88 days; expected demand during lead time 0.7.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 7 now.
  • 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
7 SET
Rp 30.3M · order by 01 Oct 2026
Expected arrival ≈ 88 days
Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
7
order qty 3
Service level
99.9%
stockout risk now 50%
Unit price
Rp 4.3M
PO history
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 107 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-506A
COOLING WATER PUMP
A1238.76

Lead time and procurement

Lead time 88 ± 54 days (PO history + category, 1 PO lines) · on-time 53%

PR dateTypeQtyUnit priceDeliveryLead time
21 Jan 2026PR03
Regular replenishment
2Rp 4.3M26 Apr 202695 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026LowPX_PP-506APP-506A high vibration
09 Sept 2026MediumPX_PP-506AReplace lamp as per PM finding
01 Aug 2026MediumPX_PP-506AOil leak at PP-506A bearing housing
20 Jun 2026MediumPX_PP-506AReplace lamp as per PM finding
11 Jun 2026LowPX_PP-506ALeak from packing
30 May 2026LowPX_PP-506AInstall scaffolding at PP-506A
28 May 2026MediumPX_PP-506APP-506A discharge pressure low
19 May 2026MediumPX_PP-506APP-506A discharge pressure low
12 Apr 2026MediumPX_PP-506AOverhaul PP-506A
31 Mar 2026LowPX_PP-506AReplace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
16 Jun 20261201000004242Corrective