RING,WEAR,DWG.715-6234,FOR PP-506A

Material 4300015352 · RING · Plant 1000

AReduceNon-moving
Material
4300015352
Category
RING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
92 d · P80 143 d
Unit price
Rp 8.2M (est.)

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~92 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 5 exceeds the level to keep (3) by 2.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 8.2M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 448.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~59 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-506A
COOLING WATER PUMP
A1238.76

Lead time and procurement

Lead time 92 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026LowPX_PP-506APP-506A high vibration
09 Sept 2026MediumPX_PP-506AReplace lamp as per PM finding
01 Aug 2026MediumPX_PP-506AOil leak at PP-506A bearing housing
20 Jun 2026MediumPX_PP-506AReplace lamp as per PM finding
11 Jun 2026LowPX_PP-506ALeak from packing
30 May 2026LowPX_PP-506AInstall scaffolding at PP-506A
28 May 2026MediumPX_PP-506APP-506A discharge pressure low
19 May 2026MediumPX_PP-506APP-506A discharge pressure low
12 Apr 2026MediumPX_PP-506AOverhaul PP-506A
31 Mar 2026LowPX_PP-506AReplace lamp as per PM finding

Recent goods issues

Never issued in the 17-month history.