Sparely
DU

BEARING,THRUST PAD,DWG.938-8400,FOR KC-3

Material 4300015573 · BEARING · Plant 1000

ALong-leadMonitorStockout
Material
4300015573
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
PERMATA SUPLINDO JAYA PT
Lead time
90 d · P80 127 d
Unit price
Rp 109.8M

Recommendation

  • 1.Forecast 0.5 SET/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~90 days; expected demand during lead time 0.1.
  • 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 07 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.2%
stockout risk now 0%
Unit price
Rp 109.8M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 353 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 269.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-396
WASH WATER BLOWER
A131.43

Lead time and procurement

Lead time 90 ± 40 days (PO history + category, 2 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
08 Jun 2026PR06
Regular replenishment
2Rp 106.6M07 Dec 2026
open
182 d
12 Aug 2025PR06
Regular replenishment
2Rp 112.9M23 Nov 2025103 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
17 May 2026LowPX_KC-396Overhaul
15 May 2025MediumPX_KC-396KC-396 bearing temp high

Recent goods issues

Posting dateQtyOrderOrder type
13 Oct 20251201000030049Corrective