BEARING,THRUST PAD,DWG.336-1886,FOR KT-2

Material 4300017635 · BEARING · Plant 1000

SReduceExcess
Material
4300017635
Category
BEARING
Base unit
SET
MRP type
Stock Item
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
130 d · P80 127 d
Unit price
Rp 123.9M

Recommendation

  • 1.Forecast 1.8 SET/year: 1.1 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~130 days; expected demand during lead time 1.1 (incl. 0.7 planned).
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 2 exceeds the level to keep (0) by 2.
Convert to Non StockSingle sourcePlanned demand in lead time
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 6%
Unit price
Rp 123.9M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 98 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~23 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-264A
TURBINE FOR KC-264A
S142.39

Lead time and procurement

Lead time 130 ± 40 days (PO history + category, 1 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
04 Jul 2025PR03
Regular replenishment
1Rp 123.9M25 Jun 2026356 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Jun 2026LowPX_KT-264ALeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
21 Oct 2025MediumPX_KT-264AKT-264A governor valve hunting
31 May 2025MediumPX_KT-264AInstall scaffolding at KT-264A

Recent goods issues

Posting dateQtyOrderOrder type
25 Jun 20261201000034485Corrective