SPRING,SAFETY VALVE,DWG.604-3310,FOR KT-

Material 4300018045 · SPRING · Plant 1000

SReduceExcess
Material
4300018045
Category
SPRING
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
123 d · P80 196 d
Unit price
Rp 16.0M

Recommendation

  • 1.Forecast 1.1 EA/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~123 days; expected demand during lead time 0.4.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 4 exceeds the level to keep (0) by 4.
Single sourceOpen PO
On hand / on order
4 / 1
next delivery 05 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 16.0M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 98 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~77 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-264A
TURBINE FOR KC-264A
S142.39

Lead time and procurement

Lead time 123 ± 65 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
18 Jul 2026PR06
Regular replenishment
1Rp 16.0M05 Oct 2026
open
79 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Jun 2026LowPX_KT-264ALeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
21 Oct 2025MediumPX_KT-264AKT-264A governor valve hunting
31 May 2025MediumPX_KT-264AInstall scaffolding at KT-264A

Recent goods issues

Posting dateQtyOrderOrder type
25 Jun 20261201000034485Corrective