TRIM SET,CONTROL VALVE,DWG.946-1608,FOR
Material 4300023747 · TRIM SET · Plant 1000
CMonitorNo stock needed
- Material
- 4300023747
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- BERKAH REFRAKTORI PRATAMA PT
- Lead time
- 199 d · P80 236 d
- Unit price
- Rp 111.0M
Recommendation
- 1.Forecast 0.3 SET/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~199 days; expected demand during lead time 0.2.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Single sourceOpen PO
On hand / on order
0 / 2
next delivery 25 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 111.0M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 304 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 10.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~75 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-465 PP-1029C OUTLET FLOW | C | 1 | 2 | 0.54 |
Lead time and procurement
Lead time 199 ± 83 days (PO history + category, 2 PO lines) · on-time 43%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 27 Jul 2026 | PR06 Regular replenishment | 1 | Rp 106.1M | 08 Jun 2027 open | 316 d |
| 09 Oct 2025 | PR06 Regular replenishment | 1 | Rp 114.6M | 25 Oct 2026 open | 381 d |
| 20 Aug 2025 | PR06 Regular replenishment | 2 | Rp 111.0M | 09 Mar 2026 | 201 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 08 Oct 2025 | Medium | PX_FCV-465 | Painting FCV-465 |
| 27 Jul 2025 | Medium | PX_FCV-465 | Overhaul FCV-465 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 01 Dec 2025 | 1 | 201000016457 | Corrective |